In August 2011 the RFCA (Reserve Forces’ and Cadets’ Association) awarded the contract to replace approximately 52m of quay wall to Southbay. The works at HMS Calliope on the bank of the River Tyne in Newcastle will see a new sheet piled wall installed behind the existing stone quay wall.

The works included:

  1. Boreholes
  2. Make existing structure safe
  3. Site Clearance
  4. Installation of Anchor tubes
  5. Install sheet pile wall
  6. Installation of ties
  7. Capping beam
  8. Drainage
  9. Concrete pavement

This site was registered with the Considerate Constructors Scheme